| AutoQty in 4 Easy Steps | ||
| AutoQty 1.0 | ||
| A Software for Automatic Quantity and Cost Calculations from AutoCAD Drawings |
||
| Using, AutoQty Software Quantities can be calculated directly from AutoCAD drawings. Note that Quantity calculation accuracy highly depends on Drawing Accuracy. All the Plans should contain required Drawing Components (Beam/ Slab /Walls etc) and should be drawn with Accuracy and To Scale. AutoQty also has a facility to 'Create your own items of Estimation', apart from items of Estimation calculated by AutoQty. There is no upper Limit of New items of Estimation. |
||
| Steps in Quantity Estimation | ||
| In order to effectively calculate the Quantities from AutoCAD Drawings the following Steps need to be strictly followed: | ||
| Step No 1: Drawing Preparation: | ||
| This is the most important step in Calculation of Quantities Drawing Preparation implies carefully arranging the drawing Components (Beam / Slab/ Column / texts etc in case of RCC Drawings and Plasters/ Walls / etc in case of Architectural Drawings) in their respective layers. For every drawing component a Layer has been specified by AutoQty The Drawing components should compulsorily be drawn in the following Layers: |
||
| LAYERS IN RCC PLAN | ||
| DRAWING COMPONENT | LAYER | REMARK |
| FOOTING | FOOT | Footings should be Rectangular or Square in shape ONLY. Each Footing should contain 4 complete Lines. Footings can be Uniform or Tapered. |
| FOOTING TEXT | FOOTTEXT | Footing Nos should be as close as possible to Centre of Footing and Drawn using 'Single Line Text' option in AutoCAD. Footing Nos should not be repeated |
| FOOTING SCHEDULE | FOOTSCH | Footing Schedule Format to be followed |
| BEAM | BEAM | Every Beam should be drawn as Double Complete Lines. Both Lines of a Beam should be of the same Length. Main Beams should be complete lines (2 Lines) touching Main Beam /Column face. Secondary Beam Lines should not Extend inside Main Beam. They should just intersect at the Main Beam Face |
| BEAM TEXT | BEAMTEXT | Beam Text should be drawn parallel to beam. Beam Text should be as close as possible to the centre of the Beam Line. |
| BEAM SCHEDULE | BEAMSCH | Beam Schedule Format to be followed |
| COLUMN | COLUMN | Columns shall be either Rectangular/ Square or Circular in shape only. Each Rectangular/ Sqaure Column should contain 4 complete Lines. Shear Walls also should be broken up into its Rectangular Columns parts and shall be designated separately |
| COLUMN TEXT | COLUMNTEXT | Column Nos should be as marked near the centre of Column and drawn parallel to Longer Dimension. |
| COLUMN SCHEDULE | COLSCH | Column Schedule Format to be followed |
| SLAB | SLAB | Every Slab be drawn as Cross Diagonal Lines to mark its extents. |
| SLAB TEXT | SLABTEXT | Slab Text to be drawn near to the intersections of the Slab Diagonal Lines using Single Line Text Option |
| SLAB SCHEDULE | SLABSCH | Slab Schedule Format to be followed |
| PCC (Plinth / Ground Floor Plan) | PCC | PCC to be drawn in Plinth / Ground Floor Plan only. PCC lines should be drawn as Diagonal lines. |
| STAIRCASE | ||
| Staircase Mid Landing Slab | SC_ML_SLAB | Every Staircase Mid Landing Slab be drawn as Cross Diagonal Lines to mark its extents. |
| Staircase Mid Landing Slab Text | SC_ML_SLABTEXT | Staircase Mid Landing Slab Text to be drawn near to the intersections of the Slab Diagonal Lines using Single Line Text Option |
| Staircase Mid Landing Beam | SC_ML_BEAM | Staircase Mid Landing Beam should be drawn as Double Complete Lines. |
| Staircase Mid Landing Beam Text | SC_ML_BEAMTEXT | Staircase Mid Landing Beam Text should be drawn parallel to Beam. Beam Text should be as close as possible to the centre of the Beam Line. |
| Riser and Tread Portion | STAIRCASE | The Central Riser and Tread Portion should be drawn as Diagonal Lines. |
| LAYERS IN ARCHITECTURAL PLAN | ||
| DRAWING COMPONENT | LAYER | REMARK |
| WALL | ||
| WALL CENTRE LINE | WALLCEN | Every Wall Type to be drawn as a single line, in a unique Color at various Wall Locations. Wall Type depends on Wall ht, thk and Unit. |
| WALL SCHEDULE | WALLSCH | Wall Schedule Format to be followed |
| PLASTER | ||
| EXTERNAL PLASTER | EXTERNAL_PLASTER | Every External Plaster Type to be drawn as a single line, in a unique Color at various External Plaster Locations. Plaster Type depends on Thickness and Height. |
| INTERNAL PLASTER | INTERNAL_PLASTER | Every Internal Plaster Type to be drawn as a single line, in a unique Color at various Internal Plaster Locations. Plaster Type depends on Thickness and Height. |
| CEILING PLASTER | CEILING_PLASTER | Every Ceiling Plaster Type to be drawn as Cross Diagonal Lines, in a unique Color at various Ceiling Plaster Locations. Ceiling Plaster Type depends on Thickness. |
| LOFT PLASTER | LOFT_PLASTER | Loft Plaster should be drawn as Cross Diagonal Lines, in a unique Color at various Loft Plaster Locations. Loft Plaster to be marked as Ceiling Plaster in Schedule. |
| PLASTER SCHEDULE | PLASTERSCH | Plaster Schedule Format to be followed |
| PAINT | ||
| EXTERNAL PAINT | EXTERNAL_PAINT | Every External Paint Type to be drawn as a single line, in a unique Color at various External Paint Locations. Paint Type depends on Thickness and Height. |
| INTERNAL PAINT | INTERNAL_PAINT | Every Internal Paint Type to be drawn as a single line, in a unique Color at various Internal PaintLocations. Paint Type depends on Thickness and Height. |
| CEILING PAINT | CEILING_PAINT | Every Ceiling Paint Type to be drawn as Cross Diagonal Lines, in a unique Color at various Ceiling Paint Locations. Ceiling Paint Type depends on Thickness. |
| LOFT PAINT | LOFT_PAINT | Loft Paint should be drawn as Cross Diagonal Lines, in a unique Color at various Loft Paint Locations. Loft Paint to be marked as Ceiling Paint in Schedule. |
| PAINT SCHEDULE | PAINTSCH | Paint Schedule Format to be followed |
| DOOR | ||
| DOOR TEXT | DOORTEXT | Each Door Text to be drawn using single Line Text Option Door Text inclination has no effect. |
| DOOR SCHEDULE | DOORSCH | Door Schedule Format to be followed |
| WINDOW | ||
| WINDOW TEXT | WINTEXT | Each Window text to be drawn using single Line Text Option Window Text inclination has no effect |
| WINDOW SCHEDULE | WINSCH | Window Schedule Format to be followed |
| OPENING | ||
| OPENING TEXT | OPENTEXT | Each Opening text to be drawn using single Line Text Option. Opening Text inclination has no effect. |
| OPENING SCHEDULE | OPENSCH | Opening Schedule Format to be followed |
| FLOORING | ||
| FLOORING | FLOOR | Every Flooring Type to be drawn as Cross Diagonal Lines, in a unique Color at various Flooring Locations. Flooring Type depends Flooring Material. |
| LOFT FLOORING | LOFT_FLOOR | Loft Flooring should be drawn as Cross Diagonal Lines, in a unique Color at various Loft Flooring Locations |
| FLOORING SCHEDULE | FLOORSCH | Flooring Schedule Format to be followed |
| MISCELLANEOUS BLOCKS | ||
| BLOCKS | BLOCKS | Items to be converted to Blocks and then inserted at desired locations |
| BLOCKS SCHEDULE | BLOCKSCH | Blocks Schedule Format to be followed |
| MISCELLANEOUS ITEMS | ||
| MISCELLANEOUS ITEMS | MSC_ITEMS | Length of Every Miscellaneous Items Type to be drawn as a single line at desired Locations. Miscellaneous Items Type depends on Height, Thk /Width and Unit. |
| MISCELLANEOUS ITEMS SCHEDULE | MSCSCH | Miscellaneous Items Schedule Format to be followed |
| CHAJJA | ||
| CHAJJA | CHAJJA | Chajja to be drawn as Cross Diagonal Lines at various Locations. |
| LOFT | ||
| LOFT | LOFT | Loft to be drawn as Cross Diagonal Lines at various Locations. |
| DADO / SKIRTING | ||
| DADO AND SKIRTING | DADOSKT | Every Dado /Skirting Type to be drawn as as a single line, in a unique Color at various Dado /Skirting Locations. Dado /Skirting Type depends on Material and Height. Dado is calculated in M2 and Skirting is calculated in M. |
| DADO AND SKIRTING SCHEDULE | DADOSKTSCH | Dado /Skirting Schedule Format to be followed |
| SPECIAL FINISHINGS | ||
| WALL SPECIAL FINISHINGS | FINISHINGS | Every Wall Finishing Type to be drawn as a single line, in a unique Color at various Wall Finishing Locations. Wall Finishing Type depends on Thickness and Height. |
| CEILING SPECIAL FINISHINGS | CEILING_FINISHINGS | Every Ceiling Finishing Type to be drawn as Cross Diagonal Lines, in a unique Color at various Ceiling Finishing Locations. Ceiling Finishing Type depends on Thickness. |
| SPECIAL FINISHINGS SCHEDULE | FINISHINGSCH | Finishing Schedule Format to be followed |
| FALSE CEILING | ||
| FALSE CEILING | FALSE_CEILING | Every False Ceiling Type to be drawn as Cross Diagonal Lines, in a unique Color at various False Ceiling Locations. False Ceiling Type depends on Thickness. |
| FALSE CEILING SCHEDULE | FALSE_CEILING_SCH | False Ceiling Schedule Format to be followed |
| WATER PROOFING | ||
| WALL WATER PROOFING | WALL_WP | Every Wall Water Proofing Type to be drawn as a single line, in a unique Color at various Wall Water Proofing Locations. Wall Water Proofing Type depends on Height. |
| FLOOR WATER PROOFING | FLOOR_WP | Every Floor Water Proofing to be drawn as Cross Diagonal Lines, in a unique Color at various Floor Water Proofing Locations. |
| WATER PROOFING SCHEDULE | WPSCH | Water Proofing Schedule Format to be followed |